tiler did up the shower kerb for both bathrooms and also did a sample mould top for my sink and hob.

raw kerb in common bathroom

raw kerb in master bathroom

hob mould on left, sink mould on right

electrician tied up loose wires, shifted light and heater switches to other side of wall and did a new concealed outlet for the study room.

wires are tied up neatly

new switches position on the left

hacked new conceal outlet for scv point and double socket

a short week ~ end of week 1.

next week, the base and titles for the kitchen base should be up, washing machine base will be constructed, aircon trunking also scheduled on thursday noon, after the deepavali holidays.